a contactor hired 150 men to pave a road in 30 days.how many mem will be hire to do the same work in 20 days​

Respuesta :

kevinmario2008 kevinmario2008
  • 05-12-2021

Answer:375

Step-by-step explanation:W = RTN

1 = 1/7500(20)N

1 = 20/7500N

1 = 2/750N

750(1 = 2/750N)

750 = 2N

750/2 = N

375 = N

There are 375 men to do the job in 20 days

Answer Link

Otras preguntas

Do you think it would be a good idea for a bumper car ride to have minimum and maximum weight requirements for riders? Apply Newton's second and third laws of m
How do cause and effect questions help you read “between the lines?”
Which inequality is represented by this graph?
In “Introduction to Found Poetry,” how does the author make the reader aware of the problem of plagiarism? by discussing the similarity between found poetry and
Line 34, "Sits on thy skin like morning dew," and line 38, "and now, like am'rous birds of prey," are examples of: O A. denotations. . O B. allusions. O c. hybe
What is (2x66)^56x20^y3 solve it plz right not a fake answer
What is the 8th term in the arithmetic sequence defined by the explicit formula An = 2n + 7
Using the model what is the mass of the aluminum atom
Evaluate Please help
can u pls help me with this question ​