It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

Respuesta :

Esther
Esther Esther
  • 03-03-2022

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job

Answer Link

Otras preguntas

suppose there are 12 year,14 year,and 16 year cicadas that all appear this yest.after how many years will all three types of cicades appear together again?
e Which of the following sentences is punctuated correctly? O "I meet you there" said Jonathan. O " "I'll meet you there," said Jonathan. O "Til meet you there"
Next 1.1 Quiz 9 Select the correct answer. The World Health Organization defines health as a balance of physical , mental, and O A. Social B. Consumer Oc. Finan
A student investigated
Someone please help me with 20 points and answer all my other questions (2 Questions) That's almost 35 points you can get. Please help. Thanks Suggest which el
help help help me pls
True or false? ( 1x77x36x89x868x757x=68x88x88x765x7)
The model represents an equation. -1 x IN Х What value of x makes the equation true? O A. -1 B. 3 D. 7 C. -7
what kind of place is lumbini​
Gavin charges $20 per hour to fix your computer. It costs him $3 for gas for each job.​